Prime Contractor Program Office

U.S.

Updated 26 October 2026Checked against the SAMM: 26 October 2026

A prime contractor program office is the team at the prime contractor that performs the contract the U.S. Government awards for a case. The purchaser is not a party to that contract, and the Department of War does not take the purchaser's direction on . The contractor must disclose to the U.S. Government any estimated offset costs included in its price.

What they do

Once the purchaser signs the , Department of War (DoW) purchasing activities and prime contractors implement its requirements through normal procurement and contract management procedures. Those procedures follow the , other directives and the contract's provisions. The should include enough detail in the for the U.S. Government () to negotiate and award the contract without the purchaser's direct involvement in the formal negotiation [SAMM ].

When an international partner accepts an , it enters a legal agreement to purchase military items or services from the . In regard to the , the international partner is the buyer, and the is the seller. The may provide the articles or services from stock, but often must contract with industry to acquire items or services for delivery to the partner [SAMM ]. In the procurement contract, the becomes the buyer, and the vendor from industry becomes the seller. The international partner is not a legal participant in the procurement contract with industry; instead, the acts on behalf of the international partner. The vendor is under contract and directly obligated to the and has no direct contractual relationship with the international partner. The vendor entering into a procurement contract with the (to produce materiel or provide services) is not exporting their products. The is exporting the products under the authority of the .

The DoW Components do not take direction from the purchaser on , or on contract terms other than the special contract provisions and warranties that condition 6.1 of the refers to. Nor may the purchaser interfere when a prime contractor places its subcontracts. To the extent Section C6.3.4 permits, however, the DoW Components may honor a purchaser's sole source request that names a specific prime or subcontract source for the defense articles or services [SAMM ].

The function is an important part of the acquisition process. The scope of involves the monitoring of all facets of implemented contracts to ensure complete and effective performance by both the contractor and the . Specialists in , quality assurance, industrial security, financial management, and production management perform . Subpart 42.3 provides a detailed listing of functions [].

Normally, there will be a assigned to the or defense agency. The oversees the contract process through the . Since the contractor may perform contract work at multiple geographic locations, it may be impractical for the to perform day-to-day oversight in administering the awarded contract. As a result, the generally delegates functions to an who is typically physically located near or at the prime contractor’s facility.

Within the DoW, the performs functions for when it is assigned as the [SAMM ]. Before , provides advice and services to help construct effective solicitations, identify potential risks, select the most capable contractors, and write contracts that meet international partner needs. After , monitors contractor performance and management to ensure that cost, product performance, and delivery schedules follow the terms and conditions of the contracts.

Quality assurance consists of inspection, testing, evaluation, and continuous verification of contractors’ inspection systems or quality assurance programs. When unfavorable conditions are detected, requirements for corrective action are initiated by the contractor. All requirements have the same quality assurance processes applied that the DoW utilizes for its own contracts. The quality assurance function includes the inspecting and ultimately accepting or rejecting the contractor’s performance under provisions of the contract. At the point of acceptance, the takes title to the materiel, which subsequently passes to the international partner at the initial point of shipment (normally the manufacturer’s loading facility for procured items) per standard term and condition 5.1. acceptance of performance is documented by either a DD Form 250, “Material Inspection and Receiving Report,” or by generating a Receiving Report acceptance within the Wide Area Workflow system.

The DoW pays contractors in accordance with the contract. Procured materiel may require “” to contractors prior to delivery [SAMM ]. These payments are made on the basis of costs incurred by the contractor as work progresses under the contract [].

distributions for procured materiel requiring are based on progress payment schedules or historical cost curves. The international partner’s should include the estimated disbursements to contractors, an appropriate contract hold-back percentage and, where no covers it, [SAMM ].

The 's position on offsets is stated in the Standard Terms and Conditions (Figure C5.F9, Section 2.8). The contractor is responsible for informing the when the pricing information it has provided includes estimated offset costs, and the contractor must disclose to the how much estimated offset cost the price includes. Those costs should be included before the is transmitted for acceptance. A request to include them after the has been accepted and implemented requires an Modification or Amendment. The includes an offset note [SAMM ].

It is inappropriate for personnel to discuss the nature or details of an offset arrangement with the purchaser. If the purchaser asks, however, the fact that offset costs have been included in the data for international competitions, or in the price estimate, may be confirmed where it is known. For answers to every question about offset agreements, their costs included, the purchaser should be directed to the U.S. contractor. involvement in any discussion of offset costs, beyond confirming that such costs are included in price estimates, must be avoided [SAMM ].

Active pipeline stages

Where this role is most involved across the FMS pipeline:

Who they work with

The most frequent counterparts across an FMS case:

Guides for this seat

References

SAMM

Public authorities

  • FAR 42.302: Federal Acquisition Regulation 42.302 (48 CFR 42.302), Contract administration functions
  • FAR 32.102: Federal Acquisition Regulation 32.102 (48 CFR 32.102), Description of contract financing methods