FMS case timeline estimator

Enter the date a went in, and the table dates each stage of the case against the targets and review periods the publishes. Where the manual sets no target, the table says so.

Estimate only — the governs. These are the manual's published targets and review periods, not a forecast for any one case.

Why real cases run longer: Why does FMS take so long?

The case

The case-development clock starts at LOR receipt; the table takes receipt as this date.

SAMM C5.T9

Stage by stage

StagePublished targetSourceEstimated date
00Pre-LOR — Requirements & Engagement
Not required. Comes before the start date.
Source—Estimated dateBefore the start date
01Letter of Request Submission
The start date.
Source—Estimated date—
02LOR Assessment
No published target.Counted inside the case-development clock, which starts at LOR receipt for Category B.The manual encourages the Implementing Agency to follow up if an LOR is not actionable within 30 days of receipt, and sets no performance standard for that period.
Source
SAMM C5.2.5.2.2fact:lor-actionable-followup-days
Estimated date—
03Case Development / LOA Preparation
85% of Category B documents within 100 days, from LOR Receipt to Offer.
Source
SAMM C5.T9fact:aod-category-b-days
Estimated dateOffer, if the standard is met—
04Congressional Notification
Not applicable to this case, as entered.
Source—Estimated date—
05LOA Offered
A single action: the offer, where the case-development clock stops.
Source—Estimated date—
06Partner Acceptance
The Offer Expiration Date is normally 85 days from Military Department Approval (MILAP): 25 days of administrative processing before the offer, then 60 days of customer review. Countries approved a longer period are the exception; those periods are not public.
SourceEstimated dateOffer expires (normal period)—
07Implementation
No published target.
Source—Estimated date—
08Execution
No published target.
Source—Estimated date—
09Reconciliation & Closure
ACCP goal: close within 24 months of supply/services complete (36 months for training cases).
Source
SAMM C16.3fact:accp-closure-months-standardfact:accp-closure-months-training
Estimated dateCounted from supply/services complete

Total

Enter an LOR submission date to date the table.

Implementation, execution and closure have no published target that runs from these dates, so the total stops at the offer's normal expiration.

Sources

Checked against the manual: 11 September 2026.