Execution is the longest phase of a case and can last many years for a major system sale. Every effort should be made to deliver in a timely manner, in line with any timelines or standards in the . The articles are bought under the same Department of War acquisition regulations and procedures as the department's own purchases, and both the time to put the letter in place and the time to award the contract add to the lead time.

How long does delivery take under Foreign Military Sales?

Every effort should be made to deliver the defense articles, services and training a purchaser buys through in a timely manner, in line with any timelines or standards the includes. Rapid delivery is concrete evidence of the U.S. commitment to its government-to-government relationship with the purchaser [SAMM ].

Acquisition for a purchaser must be carried out under Department of War (DoW) regulations and the other applicable U.S. Government procedures. Acquisition under these rules gives the foreign purchaser the same benefits and protection that apply to the DoW's own procurement. It is one of the main reasons foreign governments and international organizations prefer to buy through channels. requirements may be consolidated with U.S. Government requirements or placed on a separate contract, whichever is more expedient and cost effective. The provisions that apply to the DoW also apply to procurements, and so do all and Defense Supplement () clauses. Table C6.T1 lists selected sections with unique application to [SAMM ].

Implementation ends when the case is financially implemented in the Defense Management System, as its implementation milestone shows, unless procedures authorize otherwise [SAMM ]. Execution begins once the has processed [SAMM , ]. Execution is the longest phase in the life cycle of a . It can last many years for a major system sale case.

Acquisition in support of , both and Building Partner Capacity (), can sometimes take a long time. Long acquisition lead times can be caused by several different factors.

First, for () programs, there is the lead time. The lead time reflects the amount of time from receipt of the request until the is accepted and financially implemented. The length of this lead time depends on the ’s complexity. For programs, the serves as both the authority and funding source for the acquisition. As a result, even though the partner’s requirements are known early in the overall process, contracting actions cannot proceed until the agreement ( or case) has been accepted and financially implemented.

Second, there is the contracting administrative lead time. The contracting administrative lead time reflects the amount of time required from when the funded requirement is provided to the respective DoW until the procurement contract is awarded to a vendor. The administrative lead time is largely influenced by the time necessary to comply with the many mandatory DoW acquisition policies and procedures. Acquisition in support of is accomplished using the same acquisition policies, procedures, and management infrastructure that are utilized to make purchases for the DoW itself. Some of the actions accomplished during the administrative lead time include thoroughly identifying the requirement; performing to determine source options; developing clear specifications or statements of work/objectives; identifying an acquisition strategy; formulating a plan and evaluation criteria; advertising/soliciting for offers; allowing time for potential vendors to develop offers; evaluating competing offers; conducting discussions with industry to better understand offers; scoring industry proposals based on strengths/weaknesses/risks; selecting the offer that provides the overall best value; and awarding the contract.