The Foreign Military Sales Pipeline

The pipeline runs from stage 0 to stage 9. Pre- engagement, stage 0, is the recommended start and is not required — many cases begin with a . Congressional Notification applies above the statutory thresholds.

Select a stage to see what happens, who is involved, and what practitioners watch for.

ENGAGEMENT CASE fmsedge.com Stage 00 — Pre-LOR: Requirements & Engagement 00 Pre-LOR / Requirements & Engagement (not required) Stage 01 — Letter of Request Submission 01 LOR Submission Stage 02 — LOR Assessment 02 LOR Assessment Stage 03 — Case Development / LOA Preparation 03 Case Development / LOA Preparation Stage 04 — Congressional Notification 04 Congressional Notification (conditional) 30 days statutory (15 NATO+5) Stage 05 — LOA Offered 05 LOA Offered Expires on Offer Expiration Date (OED) Stage 06 — Partner Acceptance 06 Partner Acceptance Signature + initial deposit, before OED Stage 07 — Implementation 07 Implementation Stage 08 — Execution 08 Execution Stage 09 — Reconciliation & Closure 09 Reconciliation & Closure Meets AECA §36(b) threshold? yes → no — below §36(b) thresholds The Letter of Request starts the case Work before it is engagement, not a case. LOR Advisory IA comments to DSCA 10 working days Case development A Blanket Order, CLSSA 30 days B Defined Order 90 days C Defined Order, complicating factors 130 days D Building Partner Capacity (BPC) 60 days 85% of documents within the days shown; A, B and C count from LOR actionable AECA §36(b) notification thresholds Standard NATO+5 Major Defense Equipment $14M $25M Defense articles/services $50M $100M Design & construction $200M $300M Statutory review period 30 days 15 days NATO+5 = NATO members + Australia, Israel, Japan, Republic of Korea, New Zealand FMS Edge pipeline stage · conditional gate · below-threshold bypass · not required fmsedge.com · Current as of 26 October 2026 · SAMM C5.2 · C5.7 · C5.T9 · AECA §36(b) · DSCA 24-29

The Foreign Military Sales process in ten stages, numbered 00 to 09. The Letter of Request starts the case, and Congressional Notification is a conditional gate that applies only when a case meets an AECA §36(b) threshold. On the site, each box links to its stage page.

The Foreign Military Sales Process · Current as of 26 October 2026 · SAMM C5.2 · C5.7 · C5.T9 · AECA §36(b) · DSCA 24-29 · Download PNG

00

Pre-LOR: Requirements & Engagement

In the pre-Letter of Request phase, the U.S. Government may help a partner define its requirement before it submits a Letter of Request (LOR), though the phase is not required. The Security Cooperation Organization, the Implementing Agency and the Combatant Command help scope the requirement and plan for the Total Package Approach. A partner may also ask for price and availability before it submits the LOR.

10 key players · not required

01

Letter of Request Submission

The partner asks in writing to buy defense articles or services through Foreign Military Sales. The Letter of Request goes through the U.S. Embassy's Security Cooperation Organization or through the partner's own authorized representatives.

Single transmission; precedes Assessment · 11 key players

02

LOR Assessment

The Implementing Agency logs the Letter of Request in the Defense Security Assistance Management System on receipt, then assesses it against the mandatory actionable criteria (SAMM Table C5.T4A). A request that falls short is considered insufficient, and Requests for Information go to the purchaser. One that meets the criteria is actionable, and it is complete once the Table C5.T4B criteria are also met and every Request for Information has been addressed.

LOR Assessment standards per SAMM C5.2.5.2: Category A within 10 days, Category B within 10 days, Category C within 45 days of LOR Receipt; LOR Advisory comments are due in 10 working days; RFI cycles add time · 11 key players

03

Case Development / LOA Preparation

In case development, the Implementing Agency prepares the Letter of Offer and Acceptance data in the Defense Security Assistance Management System, and the case manager is normally responsible for its overall content. For major system sales, the case manager works with weapon system program managers and item managers to decide the line items. When the data is complete, the Implementing Agency posts the Military Department approval (MILAP) milestone and the document goes to the Defense Security Cooperation Agency for writing, review and countersignature.

Case development standards per SAMM C5.T9: Category A within 30 days, Category B within 90 days, Category C within 130 days, Category D within 60 days, each for 85% of documents, counted from LOR Actionable for Categories A, B and C and from LOR Receipt or Customer Request Complete for Category D · 11 key players

04

Congressional Notification

A Foreign Military Sales case at or above the statutory thresholds needs a numbered certification to Congress before its Letter of Offer and Acceptance may be offered. Congress first reviews the sale informally in Tiered Review, then formally for a set period, and may prohibit it only by enacting a joint resolution.

Statutory review of 30 days (15 days for NATO members, Australia, Israel, Japan, the Republic of Korea, and New Zealand); informal tiered review per SAMM C5.T24 first · 9 key players · conditional

05

LOA Offered

Once the Implementing Agency has approved the Letter of Offer and Acceptance and the Defense Security Cooperation Agency has countersigned it, the Implementing Agency signs the document and sends it to the purchaser as a formal U.S. Government offer. It stays open for acceptance until its Offer Expiration Date.

Single action; the LOA carries a standard Offer Expiration Date; extensions per SAMM C5.6.12.1 · 11 key players

06

Partner Acceptance

A partner accepts a Letter of Offer and Acceptance (LOA) when an authorized representative signs it before the offer expiration date and the partner sends the initial deposit. The purchaser also completes its fields on the LOA and sends copies to the Implementing Agency and the Defense Finance and Accounting Service, Indianapolis. Without the deposit the case does not implement.

Weeks to months depending on partner domestic approval process · 8 key players

07

Implementation

The Defense Finance and Accounting Service posts Financial Implementation once the initial deposit arrives. The Implementing Agency then processes and issues Obligational Authority (the authority to spend), and the case manager, assigned since case development, guides execution.

Implementation milestone is a single DFAS posting; transitions to multi-year execution · 8 key players

08

Execution

Contracts awarded, articles produced, deliveries made, training delivered, and the follow-on support that keeps the system operating for the rest of its life. The longest-duration stage.

10 key players

09

Reconciliation & Closure

After the last delivery, the Implementing Agency declares the case Supply/Services Complete and reconciles it for closure. Under the Accelerated Case Closure Procedures, a case with unliquidated obligations is interim closed and later final closed, and a case with none goes straight to final closure.

ACCP goal: close within 24 months of Supply/Services Complete (36 months for training cases), per SAMM C16.3.1.1.3 · 8 key players