What makes a Letter of Request actionable in Foreign Military Sales?

Updated 26 October 2026Checked against the SAMM: 2 November 2026

A is actionable once it meets the mandatory criteria in Table C5.T4A, and only then may the proceed with case development. One that falls short is insufficient, and case development cannot start until the purchaser provides or clarifies the missing information. For Category A, B and C documents, the " Actionable" milestone starts the case development clock.

THE IMPLEMENTING AGENCY FIRST, THE PURCHASER THEN DSCA WHO TELLS THE PURCHASER fmsedge.com What happens after a Foreign Military Sales Letter of Request is submitted? Recommends disapproval of MDE, SME, requested support of these articles, or the entirety of the purchaser's request SAMM C5.3.2.1 Remove or substitute the IA coordinates with the purchaser, the geographic CCMD and the SCO to remove the requirement or replace it with a comparable substitution SAMM C5.3.2.1 Foreign Military Sales Portfolio Director (DSCA) DSCA (IOPS) CPD the IA notifies the Country Portfolio Director; DSCA (IOPS) coordinates the disapproval recommendation SAMM C5.3.2.1.2 What is the U.S. embassy country team? State (PM) formally notifies the purchaser of the disapproval, through its designated Embassy representative or other appropriate channel, at DSCA's request SAMM C5.3.2.1.2 does not agree Where this applies FMS requests for defense articles, defense services, training and co-production. Routine training denials within established policy are exempt from this coordination SAMM C5.3.2.1.3 · C5.3.2.2 What makes a Letter of Request actionable in Foreign Military Sales? Development continues the case may continue; the updated requirement date may be noted with a new LOR Actionable milestone, the purchaser's acceptance submitted to DSCA in CTS SAMM C5.3.2.1.1 · C5.T15 agrees Coordinated with Foreign Military Sales Arms Transfer Office (State Department) State (PM/RSAT) FMS Team DSCA Offices OUSW(P) OUSW(A&S) [ DTSA ] if equities are identified SAMM C5.3.2.1.2 The purchaser's options the notice asks for a response within ten business days: cancel the LOR; revise it to include a comparable substitution or differing capability; or continue LOA development without the disapproved requirements, if feasible SAMM C5.3.2.1.2 the notice When the answer is not yet, or not an LOA What happens after a Foreign Military Sales Letter of Request is submitted? DSCA or State, at any time: may initiate coordination to approve or disapprove the request, or advise the IA to suspend correspondence SAMM C5.2.4 If disapproved that way: DSCA formally advises the IA to stop processing, gives the rationale, and the IA cancels the Case ID in DSAMS SAMM C5.2.4 A hold: when a unique constraint, such as an Under Secretary of War policy position, stops development, DSCA may approve a CPOHOLD SAMM C5.6.3 · C5.6.3.2 Price and Availability data or a Letter of Offer and Acceptance: what is the difference? Price and availability instead: P&A is an estimate, not a commitment to offer the articles for sale, and not valid for preparing an LOA SAMM C5.5.1 · C5.5.2 Partial LOA: the notice itself offers it: continue LOA development without the disapproved requirements, if feasible SAMM C5.3.2.1.2 FMS Edge a step on the path · who tells the purchaser · [ ]: only if equities are identified fmsedge.com · Current as of 26 October 2026 · SAMM C5.2.4 · C5.3.2 · C5.5 · C5.6.3

When the Implementing Agency recommends turning down part or all of a Letter of Request, it first tries to fix the request with the purchaser. If that fails, the recommendation goes to DSCA, and the formal notice comes from State through the embassy, asking for a response within ten business days.

When a Letter of Request is turned down · Current as of 26 October 2026 · SAMM C5.2.4 · C5.3.2 · C5.5 · C5.6.3 · Download PNG

What makes a Letter of Request actionable?

A is actionable once the , assessing it on receipt, finds that it meets the mandatory criteria in Table C5.T4A, and only then may the proceed with case development [SAMM , ]. The criteria cover the following [SAMM ]:

  • the purchaser's eligibility
  • whether the article or service may be sold
  • the channel and the authority behind the request
  • sanctions
  • whether the request is a valid military requirement
  • the type of document requested
  • the source of funding, and approval of any request for a Bank
  • enough detail for case development to begin

The also determines whether a , a endorsement, or other technical releases and policy reviews apply. If the request includes an item in the scope of the targeting infrastructure policy (), a and endorsement must already have been provided. It confirms that the purchaser is not negotiating for the same item through Direct Commercial Sales () [SAMM ].

An that does not meet these criteria is insufficient, and case development cannot start until the purchaser provides or clarifies the missing information [SAMM ]. For Category A, B and C documents, the must enter the " Actionable" milestone in the Defense Management System () before case development activities begin [SAMM ]. Categories A, B and C are case development categories of Table C5.T9: Category A covers blanket order cases and , Category B defined order cases, and Category C defined order cases with factors expected to slow their development significantly, with their amendments and, for Categories A and B, their modifications [SAMM ].

The " Insufficient" date is the date on which the assessment finds that the does not meet the mandatory criteria in Table C5.T4A. The purchaser will receive Requests for Information for whatever is needed before case development can start. The tells the purchaser promptly of an insufficient determination and records the date of that notice in . It also logs the reason the is insufficient in , using reason codes based on the Table C5.T4A criteria [SAMM ].

The " Actionable" milestone is the date on which the assessment finds that the meets at least the mandatory criteria in Table C5.T4A. The milestone is entered in the Case Milestone Window. The case must be initialized first. The milestone is mandatory for Category A, B and C documents, because it starts their case development clock [SAMM ].

The assessment, from " Receipt" to the first finding that the is actionable or insufficient, has a of 10 days for Category A, 10 days for Category B and 45 days for Category C [SAMM ]. Only that first finding counts against the standard, and the tells the purchaser promptly of the outcome and records the date of that notice in [SAMM ]. If there is a significant change to requirements already provided, the " Actionable" milestone may be entered more than once for the same case document, in accordance with C5.2.5.3 [SAMM ].

An actionable may still lack information needed to complete the . The is complete only when it also meets the criteria in Table C5.T4B [SAMM ]. Those criteria cover the following [SAMM ]:

  • the purchaser's
  • the and endorsement where one applies
  • requirements specific enough to price
  • sole source requests
  • requests to waive non-recurring costs
  • the overseas surcharge
  • a checklist of hardware, support, training, transportation and other requirements

The must enter the " Complete" milestone in before the approval () milestone [SAMM ].

Before the " Complete" date is entered in , Requests for Information will be sent to the purchaser to settle any remaining issues [SAMM ].

Partners may ask the U.S. Government () for help in working out which capability options would meet their requirements. For some partners, scoping requirements before the may be critical to submitting an actionable . The U.S. Military Group () should work with the partner, the relevant and the geographic to define the partner's requirements in full. That work may include identifying the quantity, the desired configuration, the maintenance and sustainment package, the desired delivery date, delivery and transportation considerations, training, and the services needed to support the program. The should also consider whether the requirements fit the partner's operational requirements, budget constraints and strategic objectives [SAMM ].

Where a partner asks specifically for before it submits an , the must follow the response guidance in C5.3 and C5.4. Refining these details before the lets the and the help the partner prepare actionable that address its capability gaps efficiently and effectively and stay aligned with U.S. foreign policy goals [SAMM ].