What happens when the funds on a Building Partner Capacity case expire?

Updated 9 November 2026Checked against the SAMM: 26 October 2026

A Building Partner Capacity case is paid for with U.S. appropriations, and each appropriation typically runs through three phases: current, expired and cancelled. Once the funds expire they can no longer take on new obligations without an explicit approval, only adjustments and payments against obligations already made; once they cancel they are gone for any purpose, and a later bill must be met from current funds available for the same purpose. The requires a case funded with cancelling funds to be closed by July 31st of the cancelling year.

What happens when the funds on a Building Partner Capacity case expire?

Once the funds on a expire, an is not permitted to create new obligations with them unless it has an explicit ad hoc approval to use prior-year funds [SAMM ]. Until they cancel, must use expired funds only for obligation adjustments, expenditures and outlays, and once they cancel they are no longer available for any purpose [SAMM , ].

The (POA) is the time during which is available to incur new obligations. During it, and Program Offices have the authority to use current funds for new obligations, obligation adjustments, expenditures and outlays. The Operations and Maintenance () appropriations that authorities receive have a POA of one, two, or three fiscal years (), and an appropriation expires at the end of its specific , which is September 30th unless legislation specifies otherwise. During the POA the U.S. Government () manages the funds so that residual funds are used for requirements on the case for which they were notified to Congress. The should work out whether it is beneficial to buy additional spares or accessories with residual funds instead of returning them. It does so in coordination with the Global Capability Development Directorate (/GCD) or the Regional Execution Directorate (/REX) of the Office of International Operations [SAMM ].

Expired funds keep their identity for five years after the POA ends. In coordination with the , the Country Finance Director (), Country Portfolio Director () and Regional Portfolio Director (RPD) will work to find any unused or residual funds and return them before the end of the in which the funds cancel [SAMM ].

The appropriation then cancels on September 30th of the fifth following the end of the POA. If an obligation adjustment or payment is required after that, Program Offices must look for appropriated funds currently available for the same purpose [SAMM ]. Section C15.6.1.1, "Prior Year Adjustments", covers this further.

The has overall responsibility for developing cases and training grants, obligating their funds on time, executing them and closing them. must communicate often with stakeholders such as the , RPD and , the Procuring Office, the (RA), the Military Group () and the United States Transportation Command (USTRANSCOM), so that program plans, status and changes are shared. The works closely with the RA during planning. Before it initiates a case or training grant in the Defense Management System - Module (DSAMS-BPC), it verifies that the , the Training and Equipment List () and similar documents are complete (Table C15.T2). The must know the nature and limits of the appropriated funds it uses, so that its activities meet the obligation, expiration and cancellation timelines [SAMM ].

A prior year adjustment (PYA) will be funded from the original appropriation if that appropriation is available. If its funds are not available, because they are cancelled, fully expended or committed to other efforts, the requirement must instead be funded with current-year funds that are available for the expired funds' purpose. Every PYA request requires 's approval, and the will choose an appropriate fund source and coordinate the approval with other internal stakeholders [SAMM ]. The Comptroller Directorate of 's Office of Business Operations (/) approves each request once the Office of the General Counsel in 's Front Office (FO/) and 's Financial Policy & Regional Execution Directorate (/FPRE) have reviewed it and concurred [SAMM ]. In certain instances (when the assistance exceeds the previous total program value), a Congressional Notification () may be required before the funds are authorized and released [SAMM ].

Whenever current-year funds pay for a PYA because expired-year funds are not available, the must amend the prior-year case with a unique case note stating that the funds are not available and giving the amount and the current-year case that funds the expired-year bill [SAMM ].

Before the funds cancel, the will spend them or reduce the value of the , also called a case, or of the training grant. requires the to close cases and training grants funded with expiring or cancelling funds no later than July 31st of the cancelling year, which leaves time to redirect or return residual funds before the deadline. Before that date, must make sure that vendors have delivered every item to the and submitted every invoice, and that all outstanding obligations have been paid in full. Where appropriate, the will update the Estimated Closure Date milestone in DSAMS-BPC, and it will begin closing a case or training grant as soon as the case or grant is supply/services complete [SAMM ]. Chapter 16 and Appendix 7, the Case Reconciliation and Closure Guide (RCG), give more on reconciliation and closure.

Each will send the contact information for its Closure Facilitator to (/FPRE) no later than 15 months before the funds cancel. The Closure Facilitator will send (/FPRE) a list of the contracts holding case or training grant funds that will cancel in the following . The Closure Facilitator is expected to lead the 's own stakeholders and to make sure cases and training grants close on time. The facilitator will direct the stakeholders to review the cancelling cases and training grants listed in the Management Suite () and to identify any that risk not closing by July 31st of the cancelling . The facilitator will also identify to () the valid unliquidated obligations subject to closure or cancellation, to establish whether funds remain available for later adjustments or payments against them [SAMM ]. The manual points to 7000.14-R, Volume 3, Chapter 10, paragraph 100201.D.

When the original appropriation associated with an Unmatched Disbursement (UMD) or a (NULO) has cancelled, a current and available appropriation must be used as the obligation source to resolve the (), and that source must be executed outside the [SAMM ]. For UMDs that cannot be resolved that way, should prepare a memorandum for record () for the Comptroller to consider and decide how to resolve the related to the appropriation [SAMM ].

References

SAMM

DSCA policy memoranda

  • DSCA 11-06: Execution and Closure Guidance for Pseudo Letters of Offer and Acceptance (Pseudo Cases) Financed with U.S. Appropriated Funds that have a Limited Period of Availability