How is a Building Partner Capacity program requested?

Updated 4 October 2026Checked against the SAMM: 9 November 2026

A , normally a geographic for Title 10 programs and the Department of State for Title 22 programs, plans the program. It sends its requirements to the and the in a or a similar planning document. and the assess the request, and the builds the case once the request is complete.

REQUESTING AUTHORITY: THE GEOGRAPHIC CCMD, WITH THE SCO Planning comes before the case a significant security cooperation initiative (SSCI) and an Initiative Design Document for each objective · C15.2.5.1 Memorandum of Request (MOR) detailed and coordinated, completed with the SCO, DSCA and OUSW(P), sent to DSCA · C15.2.5.1, C15.2.11 DSCA AND OUSW(P) Initiatives prioritized OUSW(P) reviews and prioritizes, USW(P) allocates resources · C15.1.6.4 DSCA reviews the MOR verifies the implementing agency and tasks it with the MOR · C15.2.11 IMPLEMENTING AGENCY (IA) Advice from the IA feedback the requesting authority uses to complete the MOR · C15.1.6.2, C15.2.5.1 if required The case is built the IA verifies the MOR is complete, then initiates the BPC case · C15.1.6.7 This path is for Title 10 funded programs, where the geographic Combatant Commands serve as the requesting authority (C15.1.6.2). USW(P) tasks the geographic CCMDs to develop and submit the SSCI objectives and Initiative Design Documents (C15.1.6.4). fmsedge.com FMS Edge a step · planning first · only if required fmsedge.com · Current as of 5 October 2026 · SAMM C15.1.6 · C15.2.5 · C15.2.11

A Title 10 funded Building Partner Capacity case starts with planning, and the request comes later. The Combatant Command plans the initiative, the Office of the Under Secretary of War for Policy (OUSW(P)) prioritizes it, and a Memorandum of Request then goes to the Defense Security Cooperation Agency (DSCA).

From an idea to a Building Partner Capacity case · Current as of 5 October 2026 · SAMM C15.1.6 · C15.2.5 · C15.2.11 · Download PNG

Who asks for a Building Partner Capacity program?

A (RA) asks for a Building Partner Capacity () program and is responsible for planning it and defining its requirements [SAMM ]. The RA also monitors the execution of the regional or partner capacity building activities it plans. The geographic combatant commands serve as RAs for Title 10 authorities [SAMM ]. The Department of State is the RA for Title 22 funded programs [SAMM ].

The at the U.S. Embassy supports the RA through each phase, from planning to the transfer of materiel or the provision of services [SAMM ].

Each geographic is responsible for multi-year planning of activities and strategies for the regions and partners within its area of responsibility, documented in the annex and the country-specific appendices of the Campaign Plan [SAMM ].

What does a request contain?

A request contains the RA's detailed requirements, sent to the and the in a pre-planning document such as a or a Training and Equipment List (). The RA completes that document using the 's feedback, and must make sure the has the information it needs to develop the case or training grant. If a requested article cannot be procured in time for expiring funds to be obligated, the RA must approve any substitution or program adjustment proposed because of cost overages [SAMM ].

For a Title 10 funded program, requirements are generated through the Significant Initiative () planning process [SAMM ]. The Office of the Under Secretary of War for Policy, known as OUSW(P), reviews and prioritizes the activities in each through the Policy Executive Council, and recommends to the Under Secretary courses of action for allocating resources [SAMM ]. An is a set of () activities, planned over several years, that serves one specific objective. It is made up of Initiative Design Documents (), and it requires Performance Monitoring Plans (). A sets out the objective statements, monitoring indicators and baseline data for the 's objectives, for its long-term and short-term outcomes, and for its outputs and activities. Each includes an Objective Tree, a logic model linking activities to objectives at three levels: the , the National Defense Strategy () and the Theater Campaign Plan (TCP) [SAMM ].

For each objective, the RA must generate an setting out the programs, projects and activities for a three-to-five-year period. The must be detailed enough that the have the information they need to source appropriate defense articles and services to achieve the objective. This planning phase ends when the RA submits a detailed, coordinated , or similar document that the can execute within the funding and timeline limits. The RA should complete the request package with support from the U.S. Military Group (), the geographic , , OUSW(P) and other stakeholders, and with the 's technical advice if required [SAMM ].

The and objective tree logic framework are linked to the Department of State’s Integrated Country Strategy (ICS) and Country-Specific Section (CSCS) of the Campaign Plan () and are designed to help determine if the request is a priority and executable.

The and objective tree logic framework help to document the initial assessment, international partner baseline, desired outcome, logic framework, theory of change, indicators and milestones, activities and resources required, monitoring plan, risks and guidance to stakeholders.

The theory of change is intended to make implicit assumptions more explicit, describe why certain actions will produce a desired change and clearly states what the intended outcome of the initiative will be and how it will be achieved. The objective tree logic framework maps goals and “SMART” (Specific, Measurable, Achievable, Relevant, Time-bound) objectives to activities necessary to achieve desired changes and visually describes activities and the planned process to achieve goals and objectives.

Once the initiative has been reviewed and prioritized, the develops the .

Before the request is final, and the will conduct a feasibility assessment. It verifies that the requirements are actionable and that the materiel and training can be provided within the restrictions of the authorizing legislation. The RA must confirm any substitute that the proposes and revise the request to match [SAMM ].

The must not share internal U.S. Government () correspondence, information about internal discussions of requirements, or pre-decisional information with Benefitting Partner representatives [SAMM ].

How does a request become a case?

A request becomes a case when the verifies that the is complete and initiates the case or training grant in the Defense Management System () [SAMM ]. This step begins when the RA submits an actionable request to as soon as possible, so that the program stays on its development timeline [SAMM ]. reviews the request, verifies the identified while it was developed, and tasks that with developing the case or training grant [SAMM ].

The Department of State, Bureau of Political-Military Affairs reviews every case and training grant to ensure that it aligns with foreign policy objectives, and approves each one [SAMM ].

The has overall responsibility for developing the case or training grant, obligating its funds on time, executing it and closing it. must communicate often with stakeholders so that program plans, status and changes are shared. Those stakeholders include the RA, the , the Procuring Office, the United States Transportation Command (USTRANSCOM) and the Country Portfolio Director (), Country Finance Director () and Regional Portfolio Director (RPD). The works closely with the RA during planning. It must know the nature and limits of the appropriated funds it uses, so that its activities meet their obligation, expiration and cancellation timelines [SAMM ].