Updated 26 October 2026Checked against the SAMM: 26 October 2026

When the moves the materiel, the purchaser usually pays a percentage of the line value set by the , charged below the line on the , or a separate case line for dedicated or special transportation. Stock from the Defense Working Capital Fund carries its first leg inside the item's price, a contractor may deliver at a price that includes transportation, and a purchaser that moves the materiel itself pays its own carrier or . A code with no percentage does not mean free transportation.

FIVE WAYS THE COST OF MOVING MATERIEL IS PAID fmsedge.com A zero rate moves the cost; it does not remove it. SAMM C9.T4A · C7.12.1 The cost of moving a materiel line “At zero”: the line’s rate in SAMM Table C9.T4A is zero, so the cost is paid one of the other ways. ON THE LOA, ABOVE THE LINE DELIVERY TERM CODES THAT USE IT the line ON THE LOA, BELOW THE LINE The percentage and the estimate are both paid into the FMS Trust Fund Transportation Cost Clearing Account. SAMM C7.12.1 · C9.17.1.1 OFF THE LOA Inside the item’s standard price Working Capital Fund items carry it in the price the exception in the SAMM glossary’s Accessorial Cost 2 and 5, on Working Capital Fund stock at zero: the cost is already in the price SAMM C9.T4A · Glossary, Accessorial Cost Its own transportation line a Special Assignment Airlift Mission or a One Time Only charter; special accessorials are added above the line too 7 or 9 at zero beside an airlift line; or 4 the airlift line carries the cost, not the materiel line SAMM C7.12.1 · C9.4.9.1.5 · C9.T4A The Delivery Term Code percentage a percentage of the line’s value, charged below the line; the rates are in SAMM Table C9.T4A and are not shown here 7, 8 and 9 on any stock; 2 and 5 on other stock a Transportation Bill Code, if used, overrides the code SAMM C9.T4 · C9.T4A · C7.12.1 An estimate of actual cost from the Transportation Cost Look-up Table, with an LOA note giving the amount by line item the line keeps its own code the estimate is used in place of the standard percentage SAMM C7.12.1 · C9.T4 The purchaser pays its own carrier collect or account-number shipments, and the onward movement it arranges itself 4 and E 4 is at zero in the table; E has no rate there SAMM C7.12.2.1 · C9.T4A Title 10 Building Partner Capacity cases are not assessed the Transportation Surcharge; a separate program-wide transportation case funds the movement (SAMM C9.T4, C15.3.11.2). No rates are shown. The Delivery Term Code percentages are in SAMM Table C9.T4A. FMS Edge a way the cost is paid · the line fmsedge.com · Current as of 12 September 2026 · SAMM C7.12 · C9.4.9.1.5 · C9.T4 · C9.T4A · C9.17 · C15.3.11.2 · Glossary

Transportation on an FMS case is paid in one of five ways, from inside a Working Capital Fund item's price to payment straight to the purchaser's own carrier. Where SAMM Table C9.T4A shows a zero rate, the cost has moved to one of the others.

How the purchaser pays for transportation · Current as of 12 September 2026 · SAMM C7.12 · C9.4.9.1.5 · C9.T4 · C9.T4A · C9.17 · C15.3.11.2 · Glossary · Download PNG

How does a purchaser pay for transportation in a Foreign Military Sale?

Under Department of War (DoW) policy, the purchaser is responsible for the transportation and delivery of the materiel it buys. The purchaser can use DoW distribution capabilities through the , on a reimbursable basis at DoW reimbursable rates. It can instead employ an agent, known as a , to manage the move from the point of origin (typically the ) to the destination it wants [SAMM ].

Advance planning for transportation by the U.S. Government and the purchaser is critical to case development and execution, and the DoW encourages purchasers to be self-sufficient by making informed decisions about their transportation arrangements. The transportation procedures in Chapter 7 generally apply to all materiel. For the Building Partner Capacity programs that the Chapter 15 introduction identifies, any requirements specific to them are in Sections C15.5 and C15-Legacy.5.6 [SAMM ].

When customers use the , a percentage is applied to the line to compute an estimated amount for transportation costs on the . percentages are based on the transportation provided (e.g., port-to-port or depot-to-in-country destination) and the rate area where articles are being delivered [SAMM , ]. may also be billed as an above-the-line charge where an estimated amount is placed above-the-line to pay for transportation services [SAMM ]. The price of Working Capital Funded () materiel includes the cost of transportation to the purchaser’s or to the . The transportation document is a Commercial or Government Bill of Lading (/). Transportation of non- materiel must be on collect commercial bills of lading (CCBLs) to the maximum extent possible []. The 7000.14-R, Financial Management Regulation () Volume 15, Chapter 7, states that, when transportation of materiel is accomplished through the use of /, normal commercial rates, not U.S. Government () rates, shall be used []. The purchaser remains responsible for onward transportation.

For a materiel line linked to a line for a flight, the should enter the appropriate against the materiel line. The code depends on the mode of transportation provided (port-to-port or depot-to-in-country destination, for example) and on the rate area of delivery. For example, a materiel line may show 7 or 9 with an Override Percent (OP) of 0%, and its remarks should state that it is a flight [SAMM ].

The must also show in the line note whether transportation is included in the price of the materiel line, or whether the U.S. Government is responsible for those costs (a non-Working Capital Fund line). In the second case, the line must show 2 paired with the other code, for example 2/7. The Distribution Screen in the Defense Management System () should then show 100% for 2 and 0% for 7, so that 2 is assessed below the line [SAMM ].

The case transportation charges document the estimated cost to the of transporting and Building Partner Capacity () materiel using the including Government Bills of Lading (). Those case transportation costs include costs for labor, materiel, or services at ports of embarkation or debarkation [SAMM ]. Defense Working Capital Fund () standard pricing includes transportation costs (for the first leg of transportation) within . If the first destination transportation is accomplished through , it must contain the funds cite. Shipping activities must clearly identify materiel as or non- to ensure the appropriate fund cite is issued for inland transportation [].

If a case line item’s vendor/contractor is providing transportation services per the contract, the transportation costs may be included in the applicable case line item’s unit and total price.

The is an industry-wide form that transportation carriers use, and it will be used as the receipt for goods, serving as proof of title and delivery. Using the is the first step toward the General Services Administration (GSA) initiative on electronic processing of transportation documents. For 4 and E shipments of materiel that is not Working Capital Fund materiel, account numbers are required, instead of collect movement, to bypass the "pre-paid" process. Within , air waybills or bills of lading convey carriage [SAMM ].

A purchaser or its may take part in choosing the carrier in two cases only: a collect shipment that requires a , or special instructions in the that apply. Most shipments to freight forwarders are pre-paid Working Capital Fund shipments. Special instructions in the are therefore inadvisable, because they do not cover pre-paid shipments and would hold up their release [SAMM ].

The purchasing country also determines its financial arrangements with the , particularly in the payment of freight bills and the provision of funds for the to pay CCBLs [SAMM ].

A is a private company under contract to the purchaser, and DoW personnel cannot direct how it conducts its operations [SAMM , ].

Small parcels are shipped prepaid by a small parcel carrier to reduce costs. The shipping activity uses pre-pay and add procedures, under which the materiel manager recovers the transportation charges from the purchaser's account. For , pre-pay and add procedures are not recommended because of a lack of in-transit visibility [SAMM ].

Try the tools: Transportation charge calculatorDelivery Term Code picker

References

SAMM

Public authorities

  • DoD FMR Vol 15: DoD Financial Management Regulation 7000.14-R, Volume 15 (Security Cooperation Policy)

Related